Sarıhıdır Hydro Electric Power Plant and Regulator

Nevsehir - Turkey

Sarıhıdır Hydroelectric Power Plant facility, the construction of which started in June 2009, was commissioned in January 2012. Sarıhıdır Hydroelectric Power Plant is one of the most special power plants in Turkey in terms of design, technology and architecture.

On this highly technical project, our team carried out construction of Hydro Electric Power Plant by directing biggest river in Turkey with 184 m3/s discharge of water on construction phase.

sarihidirHydroelectricPowerPlant.png

The plant was first of its kind on Turkey by the time, it has inflatable rubber dam which holds the water and direct it to two turbines which produces energy. It has average annual production of 23 GWh.

Installed Capacity : ~23 GWh
Date Completed : 30/01/2012
People Employed : 120
Location : Nevsehir
Total Capacity : 6,4 MWh

We are proud to finishing this project successfully and smoothly on time and ensuring our customer’s success!